Ocean Rail Bridge – 22/03/21

Works completed on site week 15-21/03:

  • All 37 concrete units for the new bridge have now been cast
  • Finishing work on the units to prepare them for blackjacking and waterproofing
  • Temporary works design for the installation of the 1000t crane pad
  • Started to remove excess cabins from site

Works planned on site (22/03 – 28/03):

  • Complete the blackjacking and waterproofing of the units
  • Continue to remove excess cabins from site
  • Continue the preparation of the 1000t crane pad
  • Demobilisation of the subcontracting team who worked on the casting of the units