
Works completed on site week 15-21/03:
- All 37 concrete units for the new bridge have now been cast
- Finishing work on the units to prepare them for blackjacking and waterproofing
- Temporary works design for the installation of the 1000t crane pad
- Started to remove excess cabins from site
Works planned on site (22/03 – 28/03):
- Complete the blackjacking and waterproofing of the units
- Continue to remove excess cabins from site
- Continue the preparation of the 1000t crane pad
- Demobilisation of the subcontracting team who worked on the casting of the units
The Ocean Rail Bridge Project page can be found here: Ocean Rail Bridge
