Ocean Rail Bridge – 12/04/21

Works completed on site 29 March to 11 April:

  • Finalise blackjacking of the bridge units

Works planned on site 12-25 April:

  • Anti-graffiti coating trial – 12-18 April
  • Trial lift and rotation of the units – starting 19-25 April
  • Ongoing investigation into cables (such as signalling and telecoms cables) through the site

The Ocean Rail Bridge Project page can be found here: Ocean Rail Bridge