Works completed on site 29 March to 11 April:
- Finalise blackjacking of the bridge units
Works planned on site 12-25 April:
- Anti-graffiti coating trial – 12-18 April
- Trial lift and rotation of the units – starting 19-25 April
- Ongoing investigation into cables (such as signalling and telecoms cables) through the site
The Ocean Rail Bridge Project page can be found here: Ocean Rail Bridge