Works completed on site week 01-07/03: 11 concrete units have been cast during the week – a higher number than what had been anticipated. To date, 31 units have been cast. In total, there are 37 concrete units to be cast on site to form the new bridge. The large units weigh up to 64t. […]
Category: Ocean Bridge Project
Ocean Rail Bridge – 01/03/21
Works completed on site week 22-28/02: 8 concrete units have been cast during the week. This brings the total number to 20 units cast to date. In total, there are 37 concrete units to be cast on site to form the new bridge. The large units weigh up to 64t. All units are planned to […]
Ocean Rail Bridge – 22/02/21
Update The results of the recent geological investigations were assessed and a decision was taken to defer the installation of the bridge to December 2021. The investigations have shown that the bedrock of the canal beneath the railway bridge is at a deeper level than reported by previous surveys. This means that construction plans have […]