Ocean Rail Bridge – 22/03/21

Works completed on site week 15-21/03: All 37 concrete units for the new bridge have now been cast Finishing work on the units to prepare them for blackjacking and waterproofing Temporary works design for the installation of the 1000t crane pad Started to remove excess cabins from site Works planned on site (22/03 – 28/03): […]

Read More… from Ocean Rail Bridge – 22/03/21

Ocean Rail Bridge – Programme Change

Ocean railway bridge replacement– change of programme Planned railway bridge replacement over the canal at Stonehouse Ocean is now expected to take place between Christmas and New Year 2021. The results of detailed geological investigations mean the bridge cannot be installed during the May Bank Holiday weekend as expected. They show that the bridge requires […]