Works completed on site week 01-07/03: 11 concrete units have been cast during the week – a higher number than what had been anticipated. To date, 31 units have been cast. In total, there are 37 concrete units to be cast on site to form the new bridge. The large units weigh up to 64t. […]
Category: News
Ocean Rail Bridge – 01/03/21
Works completed on site week 22-28/02: 8 concrete units have been cast during the week. This brings the total number to 20 units cast to date. In total, there are 37 concrete units to be cast on site to form the new bridge. The large units weigh up to 64t. All units are planned to […]
Project Update – Feb 2021
The headline this month is undoubtedly the progress being made with the Stonehouse Ocean railway bridge project. We have introduced a whole new Ocean section on this website – click here. The project is now much more recognisable now that the contractor has at long last erected a sign at the site entrance off the […]